Sunday, August 31, 2008
I'm going to bring as many tools as I can
Hi guys
Friday, August 29, 2008
Router cut everything successfully yesterday. Total cost for cutting was $60 it was $1.80 per lineal meter. This was not the l/m size of the timber but the total l/m's it took to cut each roof member. So it adds up to $6 each.
This Tuesday from 10am those who are able make it we will be working down in the 24hr space getting the timber finished.
Monday & Tuesday this week the workshop will be closed we wont be able to use any of the equipment (so everything needed on that day will have to be brought by group members) we will be able to get all our timber out of the workshop as there will be someone there all the time.
Also for those that were not there. Our allocated time for our 'complete workshop access' is Thursdays at 4pm-6pm. I know it does not suit everyone but this was the best time out of all the choices.
I am also keeping a record of payments from each person that has given money for the kitty. We are aiming to get from everyone by this Tuesday $50 to start with. So far Raffia, Joel, Jureen, Rose & myself have paid $50. Jason G. $151.20 (of materials) and Noelle $25. Can everyone who hasn't paid the total $50 or yet to pay any please get it to me this Tuesday. I am keeping a record of all expences and payments so we know how much is going out and what we have in the kitty.
Thanks
Perri
Jason as applies to everyone in the group, if you buy something for the project ensure you bring the receipt to class as we agreed on and we can divide up the funds up between the 11 of us, otherwise im sure not everyone is just going to bring money without seeing it, as happens in real life:
no receipt, no proof of purchase.
Thursday, August 28, 2008
Hey Guys!
Before any construction is done, we need the money so we can pay for it, i dont have enough money nor adriano to just go out and pay for all of it ourselves as too expensive. So make sure u bring the money adriano has sent to all of us which will cover for whats needed so far. I suggest we all bring in 100 bucks and put it somewhere and have someone take care of it, and receipts kept for the end when it will be divided up and shared out evenly, however no receipt for something bought, it comes outta your pocket for not keeping it. My suggestion.
I wont be there for the studio as have an interview for the IBL program tomorrow afternoon so if the trailer is still needed please contact me and i will organise it for pick up, just ensure it is returned after being used.
Thanks
Wednesday, August 27, 2008
Tomorrow - Friday 29th
Heres the line up for tomorrow so you all know what is happening
- Around 9am Adriano and Jason M will be picking up plywood for roof and discussing with Des Walters wether the router will be able to cut the roof structure.
- 1:45 pm (after lecture) we will need to meet up in Studio as a group to discuss together the bolts (bought for the main structure) and the options for roof brackets.
- 2pm Adriano and a few others will head down to workshop and get roof structure cut. (We have booked the router for this exact time & will probibly have it only for an hour or so).
- The rest of us will work on: Final Seat Design with its construction drawings, The Poster design, make final decision on roof fabric, steel and steelwork options. And get all the construction details finalised.
Great sorry bout all the posts..hehe...
See you all tomorrow
Perri